Estimating Costs and Determining Budgets
In
general we understand how to create the project human resource plan. To get
resources you need to spend money (Cost) and you can’t spend an infinite
amount. Every project has certain limits on the amount of money you can spend
(Budget). Here I am going to explain about estimating the costs and determining
the budget involved in a project.
Difference between Cost & Budget:
Many
people confuse the terms cost & budget and even use them interchangeably.
Unfortunately they are both not the same. So, the first thing we need,
understand clearly the difference between cost and budget.
Cost
is the value of the inputs that have been (or will be) used up to perform a
task or to produce an item: product, service, or result. This value is usually
measured in units of money. For example, you paid two programmers Rs. 5000/-
each for developing a software program, and you paid Rs.1000/- to a tester to
test the program. So, the cost for the task of developing and testing the
software program is Rs. 11,000/-. You can add the costs of components of a
system, and the sum will represent the cost of the system, but it’s still a
cost and not a budget.
Budget is an aggregated
cost with a timeline. You aggregate the costs of all the resources needed to
perform the project and put a timeline on it: the availability of funds over
time. That is called a budget. Look at the image below:
Cost management consists of estimating project costs, determining budget from the cost estimates, and controlling the cost while the project is being executed. This is just a high level depiction of cost management and we will cover the details now.
Estimating Project Costs
Estimating
project cost means developing an estimate for the monetary resources needed to
complete the project work; that is, activities. These estimates are based on
the information available at a given time. The estimates in the beginning are
less accurate; for example, their accuracy may be only as good as + or - 50
percent. For example, if you say the cost will be $50,000, it could be anywhere
between $25,000 and $75,000. As the project moves along and more information
becomes available, the cost estimates can be improved to get better estimates.
The standard process used
to estimate costs is called the Estimate Costs process. Look at the image
below:
Estimating
project cost means estimating the costs required to complete the project scope
by executing schedule activities. Therefore, you need the scope baseline and
the schedule baseline for estimating costs. The lists of items used as input to
this process are:
• Human resource plan - The
information in the human resource plan useful for estimating costs includes the
list of roles and responsibilities, personnel rates, and recognitions and
rewards.
• Project schedule - An approved
project schedule will give you the information about the resources needed to
complete the project work. This information is crucial to make cost estimates.
As you learned in the previous chapter, activity resources are estimated by
performing the Estimate Activity Resources process. Therefore, the Estimate
Costs process should be closely coordinated with the Estimate Activity Resources
process, which in turn depends on the Estimate Activity Durations process
because activity duration is determined for the given resources.
• Scope baseline - All three
components of the scope baseline; scope statement, WBS, and WBS dictionary are
useful in estimating the project cost. The scope statement will provide the
cost-relevant information, such as project and product acceptance criteria,
assumptions and constraints, product description, key deliverable, and project
boundaries around the scope.
• Risk register - Both kinds of
risks—threats and opportunities have an impact on the cost in the form of risk
mitigation costs and revenues or savings from the opportunities.
• Enterprise environmental factors
- Enterprise environmental factors relevant to estimating costs include market
conditions and published commercial information that will provide the cost of
resources, including human resources, materials, and equipment. This will also
provide the information related to the availability of products and services
and their cost and rates. Supply and demand conditions can also influence the
project cost.
• Organizational process assets -
This includes the organization’s policies regarding cost estimates, cost
estimating templates, and information from previous projects, including lessons
learned.
Determining Project Budget
Determining
the project budget is the process of aggregating the cost estimates for all
project activities and assigning a timeline to them. Cost aggregation is the
technique used to calculate the cost of a whole by summing up the costs of the
parts of which the whole is made. You can use the bottom-up estimation
technique to aggregate the costs of all the components and activities to
calculate the total cost of the project. The timeline assigned to this cost
will be important to reconcile the expenditure with the funding limits.
The
reconciliation may require rescheduling some activities.
The
budget is determined by using the Determine Budget process. Look at the picture
below:
Most of
the items in the input to this process are already described in this chapter.
Organizational process assets may include organizational policies and tools for
determining the budget. The reserve analysis at budget level includes
management reserve in addition to contingency reserve, and you must understand
the difference between the two. Contingency reserves are the funds that can be
used to deal with the unplanned events that can potentially transpire in case
one or more identified risks occur, whereas management reserves are the funds
that can be used in case of yet unplanned but future changes in some aspects of
the project, such as the project scope.
The
approved budget that includes the aggregated cost with timeline is called the
cost baseline. The cost performance of the project is monitored, measured, and
controlled against this baseline. This is why it’s also called the cost
performance baseline. Funding requirements for the project are derived from the
cost baseline and the reserve analysis.
Do not
leave out the cost of the internal employees of the organization who will work
on the project. They are not free, for two reasons: The organization pays for
them, and they do not have infinite numbers of hours to put into the project.
Their cost to the project will be determined just like any other project role
based on the hours of work they will put into the project.
In the
process of determining the budget, you may need to update the project schedule,
cost estimates, and the risk register.
Your
organization may not have the resources to complete all parts of the project.
For those parts of the project, you will need to use what is called
procurement.
Factors which change costs over time
Once
implementation begins, a project’s costs rarely remain static. As further
information becomes available the costs may be further defined. Yet, even when
a cost has become firmly fixed, there are numerous factors that can lead to the
cost increasing. Delays are a major factor. Whatever the reason, delays almost
invariably increase budget costs. Many events may have contributed to the delay
– some which could have been foreseen and others which could not.
In the
context of program funding, time and cost over-runs have obvious implications
for the number of projects that can be funded within a program period, and for
the scale of the outputs and impacts generated. These lead to projects
over-running either in time or costs. As indicated above, delays generally
translate into higher project costs.
Poor
Project Management: The
role of the project manager or project management team is probably the most
important element in containing the costs of a project. It is often true that a
poor project with a good project manager will be completed satisfactorily. But
even a good project, if combined with poor project management, will almost
always face serious difficulties.
A poor
project management structure will have an impact at all stages of the process
leading to:
• A
lack of planning and coordination;
• Poor
communication between members of the project team and the project sponsor;
• Failure
to identify problems and institute necessary design and programming changes;
• A
lack of control over time and cost inputs.
Major
or minor changes in requirement: A change in a project’s design can arise for a number of reasons. It may
be that the project sponsor wants additional elements to be included in the
project or changes to existing ones. Usually, these design changes require
additional time inputs from experts as well as the additional time and cost
inputs from the team members.
Funding
Problems: Overall lack of finance to
complete a project or delays in the payment for services by the project sponsor
can lead to significant problems arise. If the costs of a project have
increased significantly beyond the original estimate, then work on the project
may have to stop or be delayed until additional funds can be found.
Funding
problems can also arise if funds allocated to one project have been diverted to
other projects within a program of development.
Other Factors: In addition to all the categories listed
above, experience shows that problems also arise from premeditated
under-estimation of initial costs simply in order to obtain initial approval
for a project. This can lead to major projects being approved, and started, in
the knowledge that actual costs will be very much higher than the “agreed”
estimate. Once started, a high profile project is often difficult to stop. So,
when the true costs do become apparent, it is difficult for authorities to
refuse the additional funding required to complete the project.
No comments:
Post a Comment