Program (Project) Evaluation and Review Technique (PERT) is a project
management tool used to schedule, organize, and coordinate tasks within a
project. It is basically a method to analyze the tasks involved in completing a
given project, especially the time needed to complete each task, and to
identify the minimum time needed to complete the total project. PERT planning
involves the following steps:
·
Identify the specific activities and
milestones.
·
Determine the proper sequence of the activities.
·
Construct a network diagram.
·
Estimate the time required for each activity.
·
Determine the critical path.
·
Update the PERT chart as the project
progresses.
The main objective of PERT is to facilitate decision making and to
reduce both the time and cost required to complete a project. PERT is intended
for very large-scale, one-time, non-routine, complex projects with a high
degree of inter-task dependency, projects which require a series of activities,
some of which must be performed sequentially and others that can be performed
in parallel with other activities.
DESCRIPTION
PERT planning involves the following steps that are described below.
1. Identify the specific activities and milestones.
The activities are the tasks required to complete a project. The
milestones are the events marking the beginning and the end of one or more
activities. It is helpful to list the tasks in a table that in later steps can
be expanded to include information on sequence and duration.
2. Determine the proper sequence of the activities.
This step may be combined with the activity identification step since
the activity sequence is evident for some tasks. Other tasks may require more
analysis to determine the exact order in which they must be performed.
3. Construct a network diagram.
Using the activity sequence information, a network diagram can be drawn
showing the sequence of the serial and parallel activities. Each activity
represents a node in the network, and the arrows represent the relation between
activities. Software packages simplify this step by automatically converting
tabular activity information into a network diagram.
4. Estimate the time required for each activity.
Weeks are a commonly used unit of time for activity completion, but any
consistent unit of time can be used. A distinguishing feature of PERT is its
ability to deal with uncertainty in activity completion time. For each
activity, the model usually includes three time estimates:
o
Optimistic time – generally the shortest time
in which the activity can be completed. It is common practice to specify
optimistic time to be three standards deviations from the mean so that there is
a approximately a 1% chance that the activity will be completed within the
optimistic time.
o
Most likely time – the completion time having
the highest probability. Note that this time is different from the expected
time.
o
Pessimistic time – the longest time that an
activity might require. Three standard deviations from the mean is commonly
used for the pessimistic time.
PERT assumes a beta probability distribution for the time estimates. For
a beta distribution, the expected time for each activity can be approximated
using the following weighted average:
o
Expected time = ( Optimistic + 4 x Most
likely + Pessimistic ) / 6
o
This expected time may be displayed on the
network diagram.
o
To calculate the variance for each activity
completion time, if three standard deviation times were selected for the
optimistic and pessimistic times, then there are six standard deviations
between them, so the variance is given by:
[(Pessimistic - Optimistic) / 6]
5. Determine the critical path.
The critical path is determined by adding the times for the activities
in each sequence and determining the longest path in the project. The critical
path determines the total calendar time required for the project. If activities
outside the critical path speed up oe slow down (within limits), the total
project time does not change. The amount of time that a non – critical path
activity can be delayed without the project is referred to as a slack time.
If the critical path is not immediately obvious, it may be helpful to
determine the following four quantities foe each activity:
i.
ES – Earliest Start time
ii.
EF - Earliest Finish time
iii.
LS – Latest Start time
iv.
LF - Latest Finish time
These times are calculated using the expected time for the relevant
activities. The earliest start and finish times of each activity are determined
by working forward through the network and determining the earliest time at
which an activity can start and finish considering its predecessors activities.
The latest start and finish times are the latest times that an activity can
start and finish without delaying the project. LS and LF are found by working
backward through the network. The difference in the latest and earliest finish
of each activity is that activity’s slack. The critical path then is the path
through the network in which none of the activities have slack.
The variance in the project completion time can be calculated by summing
the variances in the completion times of the activities in the critical path.
Given this variance, one can calculate the probability that the project will be
completed by the certain date assuming a normal probability distribution for
the critical path. The normal distribution assumption holds if the number of
activities in the path is large enough for the central limit theorem to be
applied.
Since the critical path determines the completion date of the project,
the project can be accelerated by adding the resources required to decrease the
time for the activities in the critical path. Such a shortening of the project
sometimes is referred to as project crashing.
6. Update the PERT chart as the project progresses.
Make adjustments in the PERT chart as the project progresses. As the
project unfolds, the estimated times can be replaced with actual times. In
cases where there are delays, additional resources may be needed to stay on
schedule and the PERT chart may be modified to reflect the new situation.
BENEFITS
·
PERT is useful because it provides the
following information:
·
Expected project completion time;
·
Probability of completion before a specified
date;
·
The critical path activities that directly
impact the completion time;
·
The activities that have slack time and that
can be lend resources to critical path activities;
·
Activity start and end date.
PREREQUISITES
· Personnel should already have a good
understanding of formal project management terminology, tools, and techniques
·
PERT form template of equivalent tool (e.g.
software)
·
Create of project plan
·
Choose the most appropriate scheduling method
·
Select and organize a team to perform project
tasks.
LIMITATIONS:
The following are some of PERT's weaknesses:
·
The activity time
estimates are somewhat subjective and depend on judgement. In cases where there
is little experience in performing an activity, the numbers may be only a
guess. In other cases, if the person or group performing the activity estimates
the time there may be bias in the estimate.
· Even if the activity
times are well-estimated, PERT assumes a beta distribution for these time
estimates, but the actual distribution may be different.
Even if the beta distribution assumption holds, PERT
assumes that the probability distribution of the project completion time is the
same as that of the critical path. Because other paths can become the critical
path if their associated activities are delayed, PERT consistently
underestimates the expected project completion time.
Example: In
the following example, the Project manager knows the succession of the project
activities and the optimistic, pessimistic and most likely time (in weeks) for
the following activities:
The associated network is:
The earliest start time, earliest finish time, latest start time and
latest finish time for each activity are calculated in the following table:
No comments:
Post a Comment